Panchvati Valves & Flanges VF markPanchvati Valves& Flanges Pvt. Ltd.
Operators machining valve bodies on heavy turning centres inside the Panchvati works

Manufacturing

Two plants in MIDC Ambad, one continuous chain of custody.

Machining, heat treatment, assembly, testing and packing all happen inside our own units in Nashik. Nothing critical is subcontracted out of sight, which is why we can hold schedule when a project timeline compresses.

Facilities

Capacity built around critical-service work.

Plant I on Plot F-97 handles primary machining and heavy fabrication. Plant II on Plot E-104 carries assembly, testing and finishing. Both operate under a single ISO 9001:2015 quality system with common inspection standards.

Front elevation of Panchvati Plant I with the loading bay open

Castings, coordinated & inspected

WCB, LCB, C5/C12, WC6/WC9 and CF8/CF8M grades poured at certified partner foundries to our patterns.

Operators machining valve bodies on heavy turning centres inside the Panchvati works

Hot forging

Compact, pressure-dense drop forgings in A105, F5-F22 alloys and stainless grades.

Valve components entering a heat treatment furnace on a loading rack

Heat treatment

Controlled normalising and tempering stabilise hardness and toughness for rated service.

Assembly bay with valve bonnets being torque-bolted at Plant II

CNC machining

Multi-axis milling and turning hold API 600 / B16.34 dimensional tolerances batch after batch.

CNC lathe precision turning a steel valve disc seat face with fine metal chips

Precision turning

Seat and seal faces machined for leak-tight lapping and long cycle life.

Assembly technicians torque-bolting a large flanged valve on the shop floor

Skilled assembly

Experienced fitters build up valves with controlled torque and verified internals.

Welder performing a precision seal weld on a valve bonnet joint

Seal-welded construction

Our developed seal-welded bonnet process delivers zero-leakage valves for lethal media.

Warehouse racking holding raw valve castings and finished valves ready for dispatch

Stockholding

Deep raw-material and finished-goods stocks back urgent plant shutdowns.

Process

Seven controlled stages from enquiry to crated valve.

01

Enquiry & design review

Datasheets, line lists and specifications are reviewed against ASME B16.34 pressure-temperature ratings and available patterns before we commit a delivery date.

02

Material procurement

Castings and forgings are sourced against approved grades with mill test certificates, heat numbers recorded and carried through the build.

03

Machining

Bodies, bonnets, discs, wedges and stems machined on dedicated valve tooling, with in-process dimensional checks at each critical operation.

04

Heat treatment & hard facing

Stress relieving, normalising and annealing cycles as the grade requires, with stellite hard facing applied to seats and discs for severe service.

05

Assembly

Trim lapping, gasket and packing fitment, torque-controlled bolting and functional stroking carried out by assembly teams working to written procedures.

06

Testing & documentation

Hydrostatic shell and seat testing, air seat testing, NDE and cryogenic testing as applicable, compiled into the consignment data book.

07

Preservation & dispatch

Surface preparation, coating, flange-face protection, marking and export-grade crating before release to the freight forwarder.

Every stage signed off before the next begins.

Hold points are defined at order acknowledgement, so a client or third-party inspector always knows where the valve is.

Metrology room with a coordinate measuring machine inspecting a valve disc

Precision

Tolerance is a discipline, not an aspiration.

Sealing performance is decided in microns on the seat and disc faces. Our metrology room maintains calibrated instruments and CMM capability so dimensional conformity is verified against approved drawings rather than assumed from the machine setting.

Calibrated gauges and instruments under a controlled calibration register
CMM-based dimensional verification on critical components
Surface finish verification on seating and gasket faces
First-article inspection on new patterns and revised drawings

Next step

Want to audit the plant before you place an order?

Client and third-party audits are welcome at both units. Tell us your preferred window and we will arrange access.